Q-2, r. 16.1 - Regulation respecting the development, implementation and financial support of a deposit-refund system for certain containers

Full text
115.1. If, before the expiry of a remediation plan, a rate achieved for the year during which the plan was sent or the year following is below the rate achieved that led to the sending of the plan, extra financing must be added to the financing initially provided for in the plan. The extra financing is calculated using the equation in the second paragraph of section 115, adapted to ensure that the rate used for the calculation is the rate for the year during which the plan was sent or the year following and applies until the expiry of the plan.
If, before the expiry of a remediation plan, a rate prescribed for the year during which the plan was sent or the year following is achieved, the designated management body may cease to implement the measures in the plan with respect to that rate and the associated financing.
On the expiry of a remediation plan, if the designated management body has disbursed only part of the amount provided to finance the measures in the plan and if the rate or rates prescribed for the second year have not been achieved, it must add to the amounts provided for the financing of the measures in the next plan an amount equivalent to the amount that has not been disbursed.
O.C. 1366-2023, s. 62.